Sunday, September 30, 2007

Tower Crane Erection Process

Never seen of tower crane erection before? Here are the basic steps involved:
  1. Pile driving work based on the design by engineer.
  2. Cast a concrete base for the basic mast of the crane with timber formwork
  3. Assemble the telescopic cage section on top of basic mast
  4. Assemble the top mast section just under the mast cabin on top of cage section
  5. Erect the section of top tower containing the mast cabin above top mast section
  6. Fix the counter-jib perpendicular to the vertical tower using the counter-jib tie
  7. Hang the counterweights at the end of the counter-jib
  8. Install the main jib with the main jib tie
  9. Hang the jib trolley on the main jib

After erecting the whole tower crane, it was ready for "raising" to the required operating height. This was achieved by jacking up hydraulically the telescopic cage section and then bringing extra standard mast ( 3m height )sections into the telescopic cage consecutively until sufficient height was reached.

The fixed base-type tower crane has its tower mounted on a foundation block. By the use of another (mobile) crane, the tower can be erected to its full height at the beginning of the project or the crane can have the mechanical capability, usually hydraulically, to raise itself, allowing for the addition of structural sections to the tower.

See how's the tower crane jacking process: