Responsibilities:

  • Report to the Construction Manager / Project Manager
  • Assist the Construction Manager / Project Manager on site erection and installation matters in accordance with the design specifications, drawings, standards, data, work methods and procedures as established
  • Responsible for receiving and issuing of engineering documents and drawings for site use. Liaison with Document Controller in ensuring that the drawings and documents are correct and in order for site use
  • Responsible for the coordination and administering the site issues relating to subcontractors
  • Assist the Construction Manager / Project Manager in overseeing the site planning, management and control of the work to ensure the installation is on schedule
  • Implement procedures for the planning, scheduling, progress monitoring and reporting of all aspects of the installation, inspection, testing and commissioning
  • Liaison with Document Controller for the implementation of document control system on site and responsible for the distribution of engineering information and subsequent revised information
  • Monitor the performance, field layout, field engineering and changes
  • Liaison with safety personnel to monitor site safety in compliance with statutory and local regulations and requirements as specified in the established Safety Plan
  • Resolve field / site problems such as interpretation of drawings, specifcations, site constraints etc
  • Coordinate with T & C Team & QC Team for field testing and inspection to fulfil the specification requirements, maintain inspection records, reports and punchlist control
  • Ensure all workmanship quality objectives are implemented in accordance with the Quality Plan
  • Monitor and supervise unloading, transporting, handling and storing of equipment and materials on site
  • Ensure the quality and quantity of materials and equipment delivery are in accordance to the requirements
  • Liaison with Project Coordination Team with regards to interface issues
  • Assist Planner for the preparation of site progress report
  • Assist QS in the certification of work progress claims and any other variation claims